  • Our new music addition and administrative addition are wrapping up demolition and are beginning prep for foundation.
  •  In the new classroom (in Luther Hall) they are wrapping up drywall, installing lights and flooring, and sanding and priming to prep for paint.
  • The closing of door 2 has been postponed. Currently, you can use Door 2 for worship on
    Saturday and Sunday.
  • Additional fencing has gone up around Door 1. A big question is whether the building addition will take up the whole area of fencing causing less parking spots. Great news is this parking lot blockage is temporary. However, to move safely the crew needs this additional space during construction. By the end of the project, we will have GAINED additional parking spaces and handicap spots.